Skip to Content

Project Planning Resume

A project can be perfectly on schedule and still be behind on value: the days spent say nothing about how much of the contract has actually been earned. The two questions need to be asked side by side.

Who is it for

Companies running projects over several months, billed by progress.

How it works

  • Each activity carries its own economic value and its own estimated cost.
  • Both are spread over the planned start and end dates of the activity.
  • Every day the system recalculates how much value should have been earned by today.
  • The project totals its activities and shows the resulting margin.
  • Each figure is frozen on the project updates, so past reviews stay readable.

The result: You know whether you are ahead or behind in value, not just in days.

0.00 € 0.00 €

 Per maggiori info sui nostri moduli non esitare a contattarci

Project Planning Resume

Economic value and estimated costs of projects and tasks, prorated on the planning

Puts an economic value and an estimated cost on every task, rolls them up on the project, and prorates the value on the planned dates to answer *how much should have been achieved by today*.

Features

  • Task Value and Estimated Costs on the task; Project Value and Estimated Total Costs rolled up on the project.
  • Task Value Today – the share of the task value due today, prorated on planned_date_begindate_deadline.
  • Margin on the project, as (Project Value − Estimated Total Costs) / Project Value × 100.
  • Daily scheduled action refreshing the prorated values.
  • The figures are snapshotted on the project updates.

Main fields

Model Field Type Description
project.tasktask_valueMonetaryEconomic value of the task
project.taskestimated_costsMonetaryCosts estimated for the task
project.tasktask_value_todayFloatShare of the task value due today
project.projectproject_valueMonetarySum of the task values
project.projectestimated_costs_totMonetarySum of the task estimated costs
project.projectmarginFloatMargin percentage of the project

Demo data

  • The North Offices Upgrade project, whose three tasks sit before, across and after today, so the proration shows its three cases at once.
  • Design (finished) is due in full at 15 000.00, Building works (half way) at 30 000.00, Testing and handover (not started) at 0.00 — for a project value of 87 000.00 and a Task Value Today of 45 000.00.

Changelog

Version Notes
19.0.1.0.0 Migration to Odoo 19.0: unit tests, demo data, Italian translation and documentation.

Developed by STeSI Consulting — Francesco Moccia <moccia.f@stesi.consulting>